The variable overhead efficiency variance is the difference between the actual quantity of the cost-allocation base used and budgeted quantity of the cost-allocation base that should have been used to produce the actual output, multiplied by the budgeted variable overhead cost per unit of the cost-allocation base.
Columns 2 and 3 of Exhibit 8-1 depict the variable overhead efficiency variance. The variance arises solely because of the difference between the actual quantity (4,500 hours) and budgeted quantity (4,000 hours) of the cost-allocation base. The variable overhead efficiency variance is computed the same way the efficiency variance for direct-cost items is (Chapter 7). However, the interpretation of the variance is different. The efficiency variances for direct-cost items are based on the differences between the actual inputs used and the budgeted inputs allowed for the actual output produced. For example, a forensic laboratory (the kind popularized by television shows such as CSI and Dexter) would calculate a direct labor efficiency variance based on whether the lab used more or fewer hours than the standard hours allowed for the actual number of DNA tests. In contrast, the efficiency variance for variable overhead is based on the efficiency with which the cost-allocation base is used. Webb’s unfavorable variable overhead efficiency variance of $15,000 means that the actual machine-hours (the cost-allocation base) of 4,500 hours was higher than the budgeted machine-hours of 4,000 hours allowed to manufacture 10,000 jackets and this, because machine-hours are a cost driver for variable overhead, pushed up the potential spending on variable overhead.

The details of the table are as follows:
Actual Costs Incurred: Actual Input Quantity times Actual Rate: dollar 130,500 (which is 4,500 hours times dollar 29 per hour)
Actual Input Quantity times Budgeted Rate: 5 dollar 135,000 (4,500 hours 3 dollar 30 per hour)
Flexible Budget: Budgeted Input Quantity Allowed for Actual Output times Budgeted Rate: dollar 120,000 (which is 0.40 hour per unit times 10,000 units times dollar 30 per hour) equals 4,000 hours times dollar 30 per hour.
Level 3
Spending variance is dollar 4,500 which has favorable effect on operating income and is the difference of above sections 1 and 2.
Efficiency variance is dollar 15,000 which has unfavorable effect on operating income and is the difference of above sections 2 and 3.
Level 2
Flexible-budget variance is dollar 10,500 that has unfavorable effect on operating system and is the difference of above section 1 and 3.
The following table shows possible causes for Webb’s actual machine-hours exceeding the budgeted machine-hours and Webb’s potential responses to each of these causes.

| Possible Causes for Exceeding Budget | Potential Management Responses |
|---|---|
| 1. Workers were under-skilled and so less efficient than expected in using machines. | 1. Encourage the human resources department to implement better employee-hiring practices and training procedures. |
| 2. The production scheduler inefficiently scheduled jobs, resulting in more machine-hours used than budgeted. | 2. Improve plant operations by installing production-scheduling software. |
| 3. Machines were not maintained in good operating condition. | 3. Ensure preventive maintenance is done on all machines. |
| 4. Webb’s sales staff promised a distributor a rush delivery, which resulted in more machine-hours used than budgeted. | 4. Coordinate production schedules with sales staff and distributors and share information with them. |
| 5. Budgeted machine time standards were set too tight. | 5. Commit more resources to develop appropriate standards. |
Note how, depending on the cause(s) of the $15,000 U variance, corrective actions may need to be taken not just in manufacturing but also in other business functions of the value chain, such as sales and distribution.
As we discussed in Chapter 6, managers should not focus on meeting short-run cost targets if they are likely to result in harmful long-run consequences. In the Webb example, machines may not have been in good working condition in April 2020 because preventive maintenance had not been done in prior months to meet monthly cost targets in those months. Many companies have internal maintenance procedures so that failure to do monthly maintenance as needed raises a “red flag.”